AGENDA MEMORANDUM
Meeting Date: December 13, 2010
From: Charlie Weller, Airport Manager
Subject: Resolution authorizing a Joint Participation Agreement with the Florida Department of Transportation for funding related to the Air Navigation Approach Survey for Runway 13/31 at Leesburg International Airport
Staff Recommendation:
Staff recommends approval of the Joint Participation Agreement for funding related to the Air Navigation Approach Survey for Runway 13/31.
Analysis:
The City accepted a grant from the Federal Aviation Administration (FAA) in July 2008 to conduct an air navigation approach survey for runway 13/31. The survey is needed to establish the new precision approach because of the increased length of this runway. The survey will also identify any objects located in the runway object-free zone.
The cost of the survey performed by Hanson Professional Services, Inc. is $102,205.00. The FAA grant agreement allows for payment of 95% of that amount. Due to a communication error between staff and the FDOT, a JPA from FDOT was not issued for their standard 2.5% portion of funding until the project was well underway. FDOT rules stipulate that no work can be done until their JPA is fully executed. As a result, FDOT is now obligated to only pay a percentage of the work remaining on the project rather than the entire project cost. Therefore, the City’s funding obligation for this project will include the usual 2.5% match ($2,555.13) plus an additional amount that FDOT will not cover ($1,635.12).
Options:
1. Approve the JPA with FDOT for funding for the air navigation approach survey; or
2. Such alternative action as the Commission may deem appropriate
Fiscal Impact:
Funding for this project was included in the FY 09/10 budget and will be rolled over to the current Fiscal Year. Breakdown of project costs is as follows:
|
Funding Source |
|
|
FAA (95%) |
$ 97,094.75 |
|
FDOT (.9%) |
$ 920.00 |
|
City (4.10%) |
$ 4,190.25 |
|
Total |
$102,205.00 |
|
Department: __Airport______________ Prepared by: __Charlie Weller_______ Attachments: Yes __X__ No ______ Advertised: ____Not Required ______ Dates: __________________________ Attorney Review : Yes___ No ____
_________________________________ Revised 6/10/04 |
Reviewed by: Dept. Head ________
Finance Dept. ______JB__________
Deputy C.M. ___________________ Submitted by: City Manager ___________________ |
Account No. _031-1821-542-3130_
Project No. __310018 __________
WF No. _____301479/9_________
Budget ______________________
Available _____________________ |
RESOLUTION NO._______________
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF LEESBURG, FLORIDA, AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE A JOINT PARTICIPATION AGREEMENT WITH THE FLORIDA DEPARTMENT OF TRANSPORTATION FOR FUNDING RELATED TO THE AIR NAVIGATION APPROACH SURVEY FOR RUNWAY 13/31 AT LEESBURG INTERNATIONAL AIRPORT; AND PROVIDING AN EFFECTIVE DATE.
BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF LEESBURG, FLORIDA:
THAT the Mayor and City Clerk are hereby authorized to execute a Joint Participation Agreement with the Florida Department of Transportation whose address is Special Project Section – MS 4-521, ATTN: Ms. Holly Lopenski, 719 South Woodland Boulevard, Deland, Florida 32720, for funding related to the Air Navigation Approach Survey for Runway 13/31 at Leesburg International Airport.
THAT this resolution shall become effective immediately.
PASSED AND ADOPTED by the City Commission of the City of Leesburg, Florida, at a regular meeting held the 13th day of December, 2010