Description: AGENDAHED.JPG

Item No: 4.B.1.

 

Meeting Date: June 11, 2012

 

From: Mike Thornton, Purchasing Manager, for

Jimmy Feagle, Deputy Public Works Director

 

Subject: Ratification of City Manager purchase approval for additional work on the reconstruction of Spartan Avenue

 

 


Staff Recommendation:

Staff recommends ratification of City Manager approval for additional construction services work on the reconstruction of Spartan Avenue in the amount of $8,856.00 for a total construction services cost of $29,536.00.

 

Analysis:

City Manager approval of the additional work was required as the contractor was already mobilized and on-site reconstructing the originally contracted section of roadway. Delaying authorization of the additional work would have resulted in additional costs for remobilization.

 

The Streets Division evaluated Spartan Avenue based on citizen concerns of the condition of the roadway. Staff determined a partial base failure had occurred causing the road surface to begin failing. Removal of segments of the road base will be sufficient to adequately bring the road back to a condition that will extend the road life cycle of 15 years.

 

The Streets Division prepared a scope of work and solicited bids for the reconstruction. The scope of work included removal and replacement of 570 square yards of existing asphalt and clay road base. The contractor will use standard Florida Department of Transportation (FDOT) construction standards for the rebuild of the roadway.

 

Quotes for the originally awarded work were received from three companies and are summarized below.

 

Company Name - Location

Quoted Price

Beesley Construction Co. LLC Leesburg

$20,680.00

Paqco Inc. Leesburg

$21,260.00

CW Roberts - Wildwood

$25,376.00

 

Heavy equipment activity on the road during reconstruction caused another section of the road base and surface to fail. An additional 503 square yards of work will cost $8,856.00. This will bring the cost of the project to $29,536.00.

 

Options:

1. Ratify City Manager approval of the additional work; or

2. Such alternative action as the Commission may deem appropriate

 

 

Fiscal Impact:

The additional $8,856.00 is available in current General Fund Streets budget. Because of the base failure of the road, the nature of the project became reconstruction rather than repair. The project will need to be moved to the Capital Projects Streets division. A budget adjustment will be necessary to move the full amount or $29,536.00 from the General Fund to the Capital Projects Fund.

 

 

Submission Date and Time: 6/7/2012 11:29 AM____

 

Department: _Public Works / Streets____

Prepared by: _Mike Thornton________

Attachments: Yes____ No __X___

Advertised: ____Not Required __X___

Dates: __________________________

Attorney Review : Yes___ No ____

_________________________________

Revised 6/10/04

 

Reviewed by: Dept. Head ________

 

Finance Dept. __________________

Deputy C.M. ___________________

Submitted by:

City Manager ___________________

 

Account No. _031-5112-541.6310__

 

Project No. __310051____________

 

WF No. _____WF0743894/2_____

 

Budget _____$528,000.00_______

 

Available ____$0.00_____________