Item No: 5F.
Meeting Date: September
24, 2012
From: Mike
Thornton, Purchasing Manager for
Ray Sharp,
Public Works Director
Subject: Resolution
authorizing execution of an agreement with Leware Construction Company for the
Venetian Gardens Bridge Replacement construction services.
![]()
Staff Recommendation:
Staff
recommends approval of execution of an agreement with Leware Construction
Company for the Venetian Gardens Bridge Renovation design-build construction
services for a total not to exceed amount of $339,000.00.
Analysis:
The
purpose of this acquisition is to establish a design-build construction
services agreement with a qualified firm to accomplish the renovation of six
bridges located at Venetian Gardens.
City
Commission directed staff to issue a design-build Request for Proposal
soliciting qualified firms to submit proposals for the renovation or
replacement of the bridges located in Venetian Gardens. Commission believed a design-build approach
would be more cost effective as opposed to using the conventional
design-bid-build method of construction.
On June 20, 2012, the Purchasing
Division issued Request for Proposals (RFP) number 120302 inviting qualified
firms to submit technical and price proposals for consideration and evaluation
by the City. On July 26, 2012, the City
received technical and cost proposals from two bridge design-build construction
firms.
The City used Jones Edmunds as the
consulting engineer for the City as required by Florida State Statute. Jones Edmunds provided a minimum design
criteria package to serve as a starting point for the responding firms.
The competing firms’ technical proposals
addressed their Approach/Scheduling, Similar Project Experience and References,
and Local Business Enterprise eligibility which included information regarding
resumes, and references, organizational structure, that will be available to
the firms in providing performance of work as required by the RFP. Price proposals were also required.
Proposals
were received from the following primary and partner firms. The primary and partner firms together would
form the Design Build Team.
Primary: Leware Construction Company - Leesburg, FL
Partner: R.P. Hottinger Construction Inc. - Umatilla,
FL
Partner: Booth, Ern, Straughan and Hiott, Inc. -
Tavares, FL
Primary: Transportation Structures, Inc. – Tampa, FL
Partner: AIM Engineering & Surveying, Inc. –
Tampa, FL
For
each proposal evaluated, raw scores assigned by each member were totaled and
converted to a ranking. The rankings for
each firm were totaled and then converted to an overall ordinal score. Using this method has proven to minimize the
effects of large variances in any one evaluators’ scoring.
SUMMARY OF RANKING
|
|
Leware |
TSI |
|
|
Evaluator 1 |
Points Awarded |
94.40 |
82.65 |
|
Ranking |
1 |
2 |
|
|
Evaluator 2 |
Points Awarded |
86.85 |
76.65 |
|
Ranking |
1 |
2 |
|
|
Evaluator 3 |
Points Awarded |
88.82 |
83.24 |
|
Ranking |
1 |
2 |
|
|
Evaluator 4 |
Points Awarded |
85.64 |
75.26 |
|
Ranking |
1 |
2 |
|
|
Total Points |
355.71 |
317.80 |
|
|
Total Ordinal Rank* |
4 |
8 |
|
|
Overall Ranking |
1 |
2 |
|
SUMMARY OF PRICING
|
Bid
Item |
Leware
Const. |
TSI,
Inc. |
|
Design Total |
$35,000 |
$95,500 |
|
Base Bid: All
Wood Construction |
$271,000 |
$204,320 |
|
Alternate 1:
Composite deck |
$314,000 |
$250,550 |
|
Alternate 2:
Composite Deck and Composite Hand Rail |
$311,000 |
$285,550 |
|
|
||
|
Design Plus
Base Bid |
$306,000 |
$299,820 |
|
Design Plus
Alternate 1 |
$349,000 |
$346,050 |
|
Design Plus
Alternate 2 |
$346,000 |
$381,050 |
|
Value Engineered Contract Amount |
$339,000 |
NA |
The
Technical Qualification/Cost proposal submitted by Leware Construction Company
(LCC) was the highest ranked by the City’s technical evaluation. However, LCC increased its score over TSI due
to its initial price offer of $346,000.00 being $40,000.00 more favorable to
the City. During value engineering
discussions LCC offered several favorable suggestions leading to an additional
savings of $7,000.00. LCC design-build
approach includes the replacement of all pilings for each bridge. This approach will provide for the full
reconstruction of each bridge when the project is completed. Certainly, a much better approach than
rebuilding the top portion of the bridge on old pilings.
Following an
evaluation of LCC’s references for similar work at Disney’s Caribbean Resort,
Marriot’s Cypress Gardens, and the Phase III Hickory Nature Boardwalk projects;
the Public Works Department recommends award to the Leware Construction Company.
Options:
1. Execute an Agreement with Leware Construction
Company; or
2. Such alternative action as the Commission may
deem appropriate
Fiscal Impact:
The
Commission approved a $365,000 budget for this project. This amount is sufficient for the
design-build construction contract of $339,000.
Costs to date
for this project are:
Vendor Name Description Amount
Jones Edmunds Design
Criteria Bid Package $ 24,850
Leware
Construction Design-Build Construction $339,000
Total Project $363,850
|
Department: Public Works__________ Prepared by: Terry Pollard___________ Attachments: Yes ___X___ No _____ Advertised: Yes____________ Dates: June 19, 2012___________ Attorney Review :
Yes___ No _____
________________________________ Revised |
Reviewed by:
Dept. Head ________ Finance Dept. __________________ Deputy C.M. __________________ Submitted by: City Manager ___________________
|
Account No. 031-8124-572.63-10_____ Project No. 310081_____________ WF No. 0743901/001_________ Budget $365,000.00
__________ Available $340,127.00
__________ |
RESOLUTION NO._______________
RESOLUTION OF THE CITY COMMISSION OF THE CITY
OF LEESBURG, FLORIDA, AUTHORIZING EXECUTION OF AN AGREEMENT WITH LEWARE
CONSTRUCTION COMPANY FOR THE VENETIAN GARDEN BRIDGE RENOVATION PROJECT FOR
$339,000.00; AND PROVIDING AN EFFECTIVE DATE.
BE IT RESOLVED BY THE CITY COMMISSION OF
THE CITY OF LEESBURG, FLORIDA:
THAT the Mayor and City Clerk are hereby
authorized to execute an agreement with LEWARE
CONSTRUCTION COMPANY, whose address is 925
THOMAS AVENUE, LEESBURG, FLORIDA 34748 for Venetian Garden Bridges
Renovation pursuant to Request for Proposal 120302.
THAT
this resolution shall become effective immediately.
PASSED
AND ADOPTED by the City
Commission of the City of Leesburg, Florida, at a regular meeting held the __24th_
day of __September__ 2012.