Item No: 5D.
Meeting Date: February
25, 2013
From: Raymond
S. Sharp, Interim City Manager
Subject: Budget
Calendar for Fiscal Year 2013-14
![]()
Staff Recommendation:
Staff
recommends City Commission approval of the budget calendar for fiscal year
2013-14, which includes dates for the commission workshop meetings.
Analysis:
The
first step in the budget process is to establish a calendar for fiscal year
2013-14. By law, the City is allowed 45
days from July 1st or the date the Property Appraiser notifies the
City Commission of the certified taxable values for 2013, whichever is later,
to certify to following:
1)
the
proposed millage rate for 2013,
2)
rolled
back millage rate for 2013, and
3)
the
date, time, and place of the public hearing to consider the proposed millage
rate and tentative budget.
Since
the City may not hold a public hearing on the same date as Lake County or the
Lake County School Board, staff has tentatively scheduled the first public
hearing for September 12, 2013.
As
indicated on the attached calendar, the budget work sessions, subject to
approval and/or modification by the Commission are scheduled as follows:
February 28th- Budget Workshop/Kickoff Meeting
April 29th- Budget Workshop/Preliminary FY 13-14
Budget Information
July- 15th, 23rd, 25th
and 29th, budget/capital improvement plan workshops
July 22nd - establish the 2013 millage rate
August 1st - budget/capital improvement plan workshop
Options:
1. Approve the budget calendar, as presented, or
2. Approve the calendar as modified by the
commission
Fiscal Impact:
None
|
Department: _____Finance____________ Prepared by: ____Brandy McDaniel___ Attachments: Yes____ No ______ Advertised: ____Not Required ______ Dates: __________________________ Attorney
Review : Yes___ No ____
_________________________________ Revised |
Reviewed by: Dept. Head ______ Finance Dept. ___________ ______ Deputy
C.M. ___________________ Submitted by: City Manager ___________________
|
Account
No. __N/A___________ Project
No. ___________________ WF No.
______________________ Budget ______________________ Available
_____________________ |