AGENDA MEMORANDUM
Meeting Date: November 13, 2006
From: Jay M. Evans, Deputy City Manager
Subject: Resolution accepting the Tavares-Leesburg (Tav-Lee) Trail and Wildwood-Leesburg (Wild-Lee) Trail PD&E Studies
Staff Recommendation:
Staff recommends approval of the resolution accepting the Tavares-Leesburg (Tav-Lee) Trail and Wildwood-Leesburg (Wild-Lee) Trail PD&E Studies as prepared by Inwood Consulting Engineers, Inc.
Analysis:
The City of Leesburg contracted with Inwood Consulting Engineers, Inc. to perform Preliminary Design & Environmental (PD&E) Studies for two segments of trail that are part of the City's overall trail master plan. Both segment studies were included in the FDOT's work program and therefore funded in full by the FDOT. The City provided PD&E management through the FDOT’s Local Agency Program (LAP).
The consultant has made presentations to the Commission at regularly scheduled commission meetings during the process. No substantive changes have been made to the plan since it was presented at the July 24, 2006 City Commission Meeting.
The final report is being presented for acceptance by the City Commission.
Options:
1. Approve the resolution accepting the studies as presented; or
2. Such alternative action as the Commission may deem appropriate
Fiscal Impact:
There is no fiscal impact as a result of this action.
|
Department: ______________________ Prepared by: ______________________ Attachments: Yes____ No ______ Advertised: ____Not Required ______ Dates: __________________________ Attorney Review : Yes___ No ____
_________________________________ Revised 6/10/04 |
Reviewed by: Dept. Head ________
Finance Dept. __________________
Deputy C.M. ___________________ Submitted by: City Manager ___________________ |
Account No. _________________
Project No. ___________________
WF No. ______________________
Budget ______________________
Available _____________________ |
RESOLUTION NO._______________
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF LEESBURG ACCEPTING THE PRELIMINARY DESIGN AND ENVIRONMENTAL STUDIES FOR THE TAVARES-LEESBURG AND WILDWOOD-LEESBURG TRAILS, AS PREPARED BY INWOOD CONSULTING ENGINEERS, INC.; AND PROVIDING AN EFFECTIVE DATE.
BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF LEESBURG, FLORIDA:
THAT the Preliminary Design and Environmental (PD&E) studies prepared by Inwood Consulting Engineers for the Tavares-Leesburg Trail and the Wildwood-Leesburg Trail are hereby accepted and approved.
THAT this resolution shall become effective immediately.
PASSED AND ADOPTED by the City Commission of the City of Leesburg, Florida, at a regular meeting held the _13th____ day of __November_______ 2006
__________________________
Mayor
ATTEST:
__________________________
City Clerk