AGENDA MEMORANDUM

 

 

Meeting Date:           August 27, 2007

 

From:                          Mike Thornton, Purchasing Manager

 

Subject:                      Resolution authorizing execution of Task Order 28 with Boyle Engineering, Inc. for permit renewal and re-rate evaluation at the Turnpike Water Reclamation Facility.

 

 

Staff Recommendation:

Staff recommends execution of Task Order 28 with Boyle Engineering, Inc. for $228,731.

 

Analysis:

The City is requesting Boyle Engineering, Inc. to assist with the permit renewal and capacity re-rating evaluation for the Turnpike Water Reclamation Facility.  The Turnpike permit with the Florida Department of Environmental Protection expires July 27, 2008.

 

The engineer will complete all work necessary to obtain information required to complete the permit application.

 

Execution of Task Order 28 will authorize Boyle Engineering, Inc. to complete the scope of work necessary to apply for the permit renewal.  The work, if approved, will be performed under the existing continuing services agreement for engineering services between the city and Boyle Engineering, Inc.

 

Options:

1.  Approve execution of Task Order 28 to Boyle Engineering, Inc.; or

2.  Such alternative action as the Commission may deem appropriate

 

 

Fiscal Impact

This project will take approximately 12 months to complete.  Expenses will be incurred in the current fiscal year and the next fiscal year.  Funds are available to cover the costs estimated to be incurred this fiscal year.  If additional funds are needed this fiscal year, they will be transferred from other line item accounts.  Funds have been included in the proposed 2008 budget for the expenses that will occur next fiscal year.

 

 

Submission Date and Time:    8/24/2007 5:26 PM____

Department: _Environmental Services___

Prepared by:  _Mike Thornton__________                     

Attachments:         Yes__X_   No ______

Advertised:   ____Not Required __X___                     

Dates:   __________________________                      

Attorney Review :       Yes___  No ____

                                                

_________________________________           

Revised 6/10/04

 

Reviewed by: Dept. Head ________

 

Finance  Dept. __________________                                     

                              

Deputy C.M. ___________________                                                                         

Submitted by:

City Manager ___________________

 

Account No. _044-4099-535.31-30___

 

Project No. _  440006_____________

 

WF No. _____WF 484673  Job_  1___

                           2007-$100,000

Budget  _____ 2008-$128,731_______

 

Available ___ $ 620,927  ___________


 

RESOLUTION NO._______________

 

A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF LEESBURG, FLORIDA AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE  TASK ORDER 28 WITH BOYLE ENGINEERING, INC. FOR ENGINEERING SERVICES RELATED TO THE TURNPIKE WATER RECLAMATION FACILITY PERMIT RENEWAL AND RE-RATE EVALUATION; AND PROVIDING AN EFFECTIVE DATE.

 

BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF LEESBURG, FLORIDA:

 

            THAT the Mayor and City Clerk are hereby authorized to execute an agreement  with BOYLE ENGINEERING, INC. whose address is 320 East South Street, Orlando, Florida 32801 for engineering services related to the City’s Turnpike Water Reclamation Facility permitting and re-rate evaluation.

 

             THAT this resolution shall become effective immediately.

 

PASSED AND ADOPTED by the City Commission of the City of Leesburg, Florida, at a regular meeting held the _27th____ day of _August________ 2007.

 

 

 

                                                                            __________________________

                                                                             Mayor

 

ATTEST:

 

 

__________________________

City Clerk