Meeting Date:           November 13, 2007


From:                          Paul Kalv, Electric Director   


Subject:                      Project Plan for the Relocation of Overhead Electric Facilities Required by the FDOT Project – Highway 441 from Perkins Street to Griffin Road



Staff Recommendation:

Electric Department staff will present a project plan for the relocation of existing overhead electric facilities required by the FDOT project.  A substantial portion of the relocated facilities are proposed to be rerouted from the FDOT project area and remain overhead.


Underground loops are proposed to serve existing commercial customers located within the FDOT project area.


Existing under-utilized facilities are proposed to be upgraded to larger conductor sizes to increase the capacity of existing ties with adjacent feeders.


New switching locations are proposed along the rerouted facilities to increase system reliability and flexibility to isolate line sections that may be impacted by outages


Provision is made for the rerouting of the existing Progress Energy Florida (PEF) 69 kV overhead transmission line that will provide improve reliability and at a reasonable cost.




See staff report.




1.  Provide guidance and direction to Electric Department staff.

2.  Such alternative action as the Commission may deem appropriate


Fiscal Impact


See staff report.


Submission Date and Time:    11/8/2007 11:46 AM____


Department: ______________________

Prepared by:  ______________________                     

Attachments:         Yes____   No ______

Advertised:   ____Not Required ______                     

Dates:   __________________________                     

Attorney Review :       Yes___  No ____



Revised 6/10/04


Reviewed by: Dept. Head ________


Finance  Dept. __________________                                     


Deputy C.M. ___________________                                                                         

Submitted by:

City Manager ___________________


Account No. _________________


Project No. ___________________


WF No. ______________________


Budget  ______________________


Available _____________________