AGENDA MEMORANDUM

 

 

Meeting Date:           August 25, 2008

 

From:                          Mike Thornton, Purchasing Manager             

 

Subject:                      Resolution authorizing  continuing services agreements with Kimley-Horn and Associates, Inc. and GMB  Engineers & Planners, Inc. for future traffic signal and intersection management professional engineering services

 

 

Staff Recommendation:

Staff recommends approval of the resolution authorizing execution of continuing services agreements with Kimley-Horn & Associates, Inc. and GMB Engineers & Planners, Inc.

 

Analysis:

The purpose of this solicitation is to establish a continuing services agreement with two qualified firms to provide professional engineering services regarding traffic signal and intersection design and management as provided by FS 287.055, the Consultant’s Competitive Negotiations Act (CCNA). 

The scope of professional services includes all services related to traffic signal and intersection design.  The City has very few signalized intersections under its control.  For those signalized intersections that do fall under City control, Lake County maintains under an existing agreement with the City. 

 

The City has been using traffic engineering services for design services related in upgrading FDOT intersections within the city limits from concrete strain pole to structural metal mast arms.  For future projects, the City will negotiate the technical aspects of the scope of work, deliverables, schedule and fee on a project-by-project basis.   Tasks will be estimated and billed at hourly rates in accordance with the professional’s fee schedule.

 

On February 11, 2008, the Purchasing Division issued Request for Qualifications (RFQ) number 80112 inviting interested and qualified firms to submit a Statement of Qualifications for consideration and evaluation by the City.  On March 10, 2008, the City received qualification statements from six engineering firms.  An evaluation committee consisting of staff from the Public Works department evaluated the SOQ’s.  The result of those evaluations is detailed in the ranking list included here.

 


SUMMARY OF RANKING

 

Engineering Firm                                                      Rank

Kimley-Horn Associates, Inc.

    1

GMB Engineers & Planners, Inc.

    2

Volkert & Associates, Inc.

    3

Dyer, Riddle, Mills, Precourt

    4

Neel-Schaffer, Inc.

    5

T.Y. Lin International

    6

 

For each SOQ evaluated, raw scores assigned by each member were totaled and converted to a ranking.  The rankings for each firm were totaled and then converted to an overall ordinal score.  Using this method has proven to minimize the effects of large variances in any one evaluators’ scoring.

 

Options:

1.  Execute an Agreement with the firms listed; or

2.  Such alternative action as the Commission may deem appropriate

 

Fiscal Impact:

The fiscal impact is not determinable at this time.  As future projects are identified and budgeted, commission approval will be sought when required.

 

Submission Date and Time:    8/21/2008 5:08 PM____

 

Department:  Public Works____________

Prepared by: Terry Pollard__________                     

Attachments: Yes ___X___   No   ______

Advertised:    Yes________________                     

Dates:             February 13, 2008________                                 

Attorney Review :       Yes___  No _____

                                                

_________________________________           

Revised 6/10/04

 

Reviewed by: Dept. Head ________

 

Finance  Dept. ____________JB____                                     

                              

Deputy C.M. ______EFS__________                                                                         

Submitted by:

City Manager ___________________

 

Account No. N/A_________________

 

Project No.   N/A_________________

 

WF No.          N/A_________________

 

Budget           N/A_________________

 

Available       N/A__________________